All articles
Example·7 min read

Electrical Proposal Example: A Complete Sample You Can Copy

A complete electrical proposal example for a 100 A to 200 A service upgrade with three new circuits: counted scope, itemized pricing, permit and inspection, exclusions, payment schedule, warranty and signature block.

Published November 11, 2026

Plenty of advice tells you what an electrical proposal should contain. Fewer places show you a finished one. Below is a complete example for the residential job most electricians quote every month: a 100 A to 200 A service upgrade, with a few new circuits added while the power is off. Every section is filled in the way it should read when it lands in a homeowner's inbox. If you want the reasoning behind each part first, that lives in how to write an electrical proposal.

The contractor, the client, the address and the license number are fictional, and the numbers are an example, not market rates. Your prices will differ by region, utility and house. Copy the structure; swap in your own figures.

The example, section by section

ELECTRICAL SERVICE UPGRADE PROPOSAL
Proposal #RE-2026-0412 · November 11, 2026 · valid 30 days
Ridgeway Electric LLC · License #EC-000000 (example) · (614) 555-0137
Prepared for: Marcus & Elena Duarte · 2218 Linden Hollow Rd, Columbus, OH
1. Project summary
Replace the existing 100 A service and panel with a new 200 A service and main breaker panel, sized from a load calculation covering the home's existing loads plus a planned EV charger and a basement workshop. Add three new dedicated circuits while the service is down.
2. Scope of work
• Coordinate the utility disconnect and reconnect for the service change
• Remove the existing 100 A panel, meter base and service entrance cable
• Install a new Square D QO 200 A, 40-space main breaker load center
• Install a new meter base, service mast and service entrance conductors
• Bring grounding and bonding up to the current local code
• Transfer all existing circuits (22) to the new panel and label a new panel directory
• New circuit 1: 50 A, 240 V circuit to a receptacle in the garage for an owner-supplied EV charger
• New circuit 2: 20 A dedicated circuit with two receptacles at the basement workbench
• New circuit 3: 20 A dedicated circuit for the basement freezer
• AFCI and GFCI protection on new circuits where the local code requires it
3. Investment
Materials
200 A main breaker panel with breakers$1,180
Meter base, mast, service entrance conductors, fittings$640
Grounding electrodes, conductor and clamps$210
Wire, boxes and devices for 3 new circuits$470
Materials subtotal$2,500
Labor
Service change and circuit transfer (2 electricians)$3,680
Grounding and bonding$420
Three new circuits, run, terminated and tested$1,140
Permit application, inspections, utility coordination$360
Labor subtotal$5,600
Total$8,100 + tax
4. Permit, inspection and code
Ridgeway pulls the electrical permit and schedules and attends every inspection required by the local authority. The permit fee itself is passed through at cost, with the receipt, on the final invoice. All work is performed to the electrical code as adopted by the local authority having jurisdiction. The utility restores power only after the service passes inspection.
5. Allowances, exclusions and hidden conditions
Allowance: up to 3 hours of repair to existing wiring found unfit for connection at the panel, at $95 per hour, billed only if used. Excluded: drywall or plaster repair and painting beyond rough patching; any utility company fees or work on the utility side of the meter; the EV charger unit; trenching; remediation of knob-and-tube or aluminum branch wiring; correcting existing violations outside the work area. If we find a hidden condition, we stop, document it, and price it as a written change order before going further.
6. Schedule
Two working days. Power to the house will be off for most of the service-change day; the exact date depends on the utility's disconnect schedule, which we confirm with you once the permit is issued.
7. Payment
Deposit of $2,430 on acceptance to schedule the work and order the panel. $3,240 when the new service passes inspection and power is restored. Balance of $2,430 when the new circuits pass final inspection.
8. Warranty
Equipment: panel, breakers and devices carry the manufacturer's warranty, on the manufacturer's terms. Workmanship: Ridgeway warrants the installation for 2 years from final inspection.
9. Acceptance
This proposal is valid for 30 days. Signing below accepts the scope, price and terms above.
Client signature: ______________________ Date: __________
Ridgeway Electric LLC: ______________________ Date: __________

Why each section is there

The summary names the reason for the size.“Sized from a load calculation” tells the homeowner the 200 A recommendation is arithmetic, not an upsell, and it lists the loads they told you about, so they can see you listened.

The scope is counted.Twenty-two circuits transferred, three new ones, each with its amperage and what it serves. When the client asks mid-job whether you could “just add” two outdoor receptacles, the list answers for you: that is a change order, not a favor.

Materials and labor are split. A panel can be priced online in a minute. Showing materials openly makes the labor line read as what it is: the licensed part of the job.

The permit has its own section. This is where you separate yourself from an unlicensed bid. Saying who pulls the permit and who attends inspections turns your higher price into the cost of doing it properly. Keep the code sentence general and true; the how-to guide explains why a clean general statement beats a list of article numbers you might get wrong.

The allowance and exclusions handle the walls. Old houses hide things. A small, stated allowance and a written change-order clause stop you from either eating the surprise or arguing about it.

Payments follow inspections. The client trusts the inspector, so tying each payment to a passed inspection makes the schedule feel fair. The three payments add up to the total exactly, which is worth checking on every proposal you send. Deposit limits and required contract wording vary by state and province, so check your local rules before you copy the percentages.

Small jobs: when one page is enough

Not every electrical job needs nine sections. A service call, a single new circuit, a few fixtures swapped, or an EV charger circuit on a panel with room to spare can go out as a one-page quote: what you will do, the price, what is excluded, the permit line if one applies, and a signature. The guide on how to make a quote for a job covers that shorter format, and the job quote generator produces it.

Small jobs are also where a fixed price is hardest, because you rarely know what is behind the first cover plate. Many electricians bill this work by the hour instead. If you do, say so on the page: the hourly rate, how materials are charged, an estimate of the hours if you can give one, and a not-to-exceed figure you will not go past without the client's written approval. Whether a not-to-exceed figure binds you, and how, depends on your contract and local rules, so treat it as common practice rather than a legal formula.

How to produce one quickly

Typing all of this for every bid is the slow part. ProposalPro builds a proposal like the one above from a short job form, or you can dictate the job and let it fill the form for you. It writes the scope, exclusions, payment schedule and warranty around the numbers you give it, and it does not invent prices, brands or warranty terms you did not enter. The electrician proposal template is the starting point for this trade, and the template gallery shows the finished designs.

For hourly work, you can now choose time and materials as the pricing: an hourly rate, with an optional materials markup, estimated hours, estimated materials and a not-to-exceed cap. The app does the arithmetic itself and labels any total as an estimate; if you give only the rate, the proposal shows the rate and no invented total. It does not recalculate the money section if you edit the document by hand afterwards.

The free plan gives you 3 proposals a month with a watermarked PDF. Sending a link the client can sign online is part of Pro. If you want to see your own panel job written up this way, start a free account and try it on the next quote you owe someone.

Frequently asked questions

What should an electrical proposal include?

A short project summary, a counted scope (circuits, panel work, devices), materials and labor priced separately, who pulls the permit and attends inspections, allowances and exclusions with a change-order clause, a schedule, a payment schedule, the manufacturer and workmanship warranties, a validity period, and a signature block.

Is there a free electrical proposal template?

Yes. You can copy the structure of the example in this post into your own document, or let ProposalPro write it from your job details: the free plan includes 3 proposals a month as watermarked PDFs.

What is the difference between an electrical proposal, an estimate and a bid?

An estimate is an approximate price, often given before the scope is fixed. A bid is a price submitted to compete for a defined job, usually against other contractors. A proposal is the full written offer: scope, price, exclusions, payment terms and warranty, ready for the client to accept.

How long should an electrical proposal be?

Two to three pages for a service upgrade or a larger residential job. A service call, a single circuit or an EV charger circuit on a panel with spare capacity can go out as a one-page quote with the work, the price, the exclusions and a signature line.

Can a client sign an electrical proposal online?

In ProposalPro, yes on the Pro plan: you send a share link and the client accepts with a typed signature. On the free plan you download the PDF and collect the signature yourself.

Write your next proposal in 2 minutes

ProposalPro generates the whole thing, scope, pricing, and terms, in a template your client can accept online. Free to start.

Start free